Opinion

Pleasant View: What do the studies reveal, and on what technical basis did the demolition committee conclude that demolition was necessary?

Photo credit : Photo by William Crooks Référence : https://qcna.qc.ca/north-hatleys-pleasant-view-beach-house-set-to-be-replaced-after-unanimous-demolition-vote/ It has now been more than 30 days since the construction

NH

North Hatley Info

August 23, 2026 · 10 min read

Photo credit : Photo by William Crooks
Référence : https://qcna.qc.ca/north-hatleys-pleasant-view-beach-house-set-to-be-replaced-after-unanimous-demolition-vote/


It has now been more than 30 days since the construction contract for the new Pleasant View Community Centre was awarded, for a total amount of $4,078,000 (reference SEAO).

This contract is the culmination of a lengthy process that led the Municipality of North Hatley from an initial project to renovate the historic Pleasant View building, estimated at approximately $1.596 million, to its demolition and the construction of a new building at a cost of $4.078 million in the coming weeks.

The evolution of this project was based on several studies, analyses and professional reports. Some of these documents played a decisive role in the decision to demolish the building.

However, these documents, which are essential to understanding the decision, do not appear to be publicly accessible.


The Studies and Expert Reports at the Heart of the Decision to Authorize the Demolition

It should be recalled that the geotechnical study, at a cost of $12,350, as well as the structural analysis of the building, enabled the Demolition Committee, composed of elected officials Andrew J. Pelletier, Caroll Haller and Danielle Dupré, to confirm the fragility of the structure, preventing it from being moved and leading to its demolition.

The October 7, 2024 resolution states that the committee made its decision “in light of the studies and expert reports.”

It indicates:

June 2024:

  • receipt of the geotechnical study;
  • structural analysis of the existing building.

Then, in:

August 2024:

  • receipt of the structural analysis;
  • confirmation of the fragility of the structure.

The resolution then explains that the building is located within constraint zones and that the project is not eligible under the applicable regulatory framework in its current location, since it would be possible to move the building outside these zones.

But it adds a decisive element:

the structural study of the building demonstrates that its structure will not be able to withstand being moved and that demolition followed by reconstruction will therefore be required.

It was therefore presumably between the return of the technical analyses in June and August 2024 that the renovation project definitively shifted toward demolition followed by reconstruction.

The question remains, however: What exactly do these studies contain, and on what technical findings did the Demolition Committee rely to conclude that demolition was necessary?

Reference: Minutes of October 7, 2024 — Resolution 2024-10-07.17

View the October 7, 2024 municipal minutes


Questions That Remain

After more than two years of proceedings, and now that a $4.078 million contract to demolish the existing building and construct a new one has been awarded, several questions deserve documented answers:

What exactly does Granulab’s geotechnical study conclude, and where can the study report be consulted?

What exactly does the structural analysis received in 2024 conclude, and where can the study report be consulted?

Which report determined that the building could not be moved, and where can that report be consulted?

What options for preserving the building were studied, and where can those options be consulted?

Was the reconstruction of the foundations, which was still part of the project in January 2024, the subject of a comparative analysis, and where can that comparative analysis be consulted?

What were the estimated costs of the various options?

Which reports and expert assessments were presented to the three elected officials on the Demolition Committee before their vote?

The October 7, 2024 resolution itself states that the committee made its decision “in light of the studies and expert reports.”

Making these documents available would simply allow citizens to review the same technical information that was used to make the decision.

For a public project of this magnitude, this would make it possible to clearly understand what was studied, what was rejected, and why.

With that in mind, please provide me with these documents when they become available, ideally before demolition work begins.


From a Renovation Project to Complete Demolition

One important element of the file is sometimes overlooked: the project did not begin as a demolition project.

Resolution 2024-10-07.17 of the Municipal Council indicates that, in May 2023, the Municipality submitted an application for financial assistance under the PRACIM program specifically for the renovation of the Pleasant View building.

The project was subsequently pre-selected, and the estimated cost of renovating and bringing the building up to code was approximately:

$1,596,000

Reference: Minutes of October 7, 2024 — Resolution 2024-10-07.17

View the October 7, 2024 municipal minutes


January 2024: The Municipality Was Still Considering Preserving the Building

On January 23, 2024, the Municipality authorized a geotechnical study.

Resolution 2024-01-23.04 is particularly noteworthy because it still describes the project as a reconstruction/renovation project for the Pleasant View building.

It also specifies that the project was to include the reconstruction of the foundations.

The geotechnical study was required to assess the bearing capacity of the soil and foundations in relation to the project.

At that point, the complete demolition of the building therefore did not yet appear to be the option that had been selected.

Reference: Minutes of January 23, 2024 — Resolution 2024-01-23.04

View the January 23, 2024 municipal minutes


March 2024: A $12,350 Geotechnical Study

On March 4, 2024, Council returned to the project.

Resolution 2024-03-04.08 still explicitly refers to the:

“Pleasant View building renovation project”

It specifies that the geotechnical study was required to determine the exact structural recommendations required for the project.

Three companies had been invited to submit bids:

  • Granulab: $12,350
  • FNX Innov: no bid
  • NCL Envirotek: no bid

The contract was therefore awarded to Granulab for $12,350.

Reference: Minutes of March 4, 2024 — Resolution 2024-03-04.08

View the March 4, 2024 municipal minutes


Demolition Committee Appointed in March 2024

During the same meeting on March 4, 2024, Council appointed the Demolition Committee.

According to Resolution 2024-03-04.10, the municipal by-law requires that the committee be composed of three members of Municipal Council.

The appointed members were:

  • Andrew J. Pelletier — Chair
  • Caroll Haller — Member
  • Danielle Dupré — Member

The same resolution appointed the following alternate members:

  • Elizabeth Fee
  • David Wilson

This composition is particularly relevant to the Pleasant View file, since this committee would be called upon a few months later to rule on the demolition of the building.

It is important to point out that this was therefore not an independent committee made up of experts in architecture, heritage, structural engineering or geotechnical engineering: all three committee members were elected municipal officials.

Their decision therefore had to rely, among other things, on the studies, analyses and expert reports presented to them.

Reference: Minutes of March 4, 2024 — Resolution 2024-03-04.10

View the March 4, 2024 municipal minutes


May and July 2024: Preliminary Plans

In May 2024, Council authorized a call for tenders for the preparation of preliminary plans and specifications for the project.

The corresponding resolution is 2024-05-06.23.

Then, on July 8, 2024, Council awarded David Leslie Architecte an $8,500 plus taxes mandate for preliminary architectural planning.

Interestingly, the July 8 resolution still describes the file as a:

Pleasant View building renovation project submitted to PRACIM.

Two proposals had been received:

  • Firme 1628 Inc.: $21,200
  • David Leslie Architecte: $8,500

The contract was awarded to David Leslie.

References:

Minutes of May 6, 2024 — Resolution 2024-05-06.23

View the May 6, 2024 municipal minutes

Minutes of July 8, 2024 — Resolution 2024-07-08.13

View the July 8, 2024 municipal minutes


June and August 2024: The Turning Point

This is where the timeline becomes particularly interesting.

In its October 7, 2024 resolution, the Municipality itself reconstructs the steps that led to demolition.

It indicates:

June 2024:

  • return of the geotechnical study;
  • structural analysis of the existing building.

Then:

August 2024:

  • return of the structural analysis;
  • confirmation of the fragility of the structure.

The resolution then explains that the building is located in constraint zones and that the project is not eligible under the applicable regulatory framework in its current location, since it would be possible to move the building outside those zones.

But it adds a decisive point:

the structural study of the building demonstrates that its structure will not be able to withstand being moved and that demolition followed by reconstruction will therefore be required.

It was therefore presumably between the return of the technical analyses in June and August 2024 that the renovation project definitively shifted toward demolition followed by reconstruction.

Reference: Minutes of October 7, 2024 — Resolution 2024-10-07.17

View the October 7, 2024 municipal minutes


September 3, 2024: Public Consultation on the Demolition

A public consultation of the Demolition Committee was held on September 3, 2024.

An article in The Record, published the following day by QCNA and written by William Crooks, provides a particularly interesting account of the meeting.

According to the article, the information presented during the consultation included:

  • a severely deteriorated foundation;
  • significant cracks;
  • ongoing movement of the building;
  • unstable soil conditions;
  • instability compared to “quicksand”;
  • stabilization that would have been costly and potentially temporary;
  • no guarantee that stabilization would prevent further damage;
  • the building’s location within a flood zone and shoreline buffer.

The article also reports that the project manager presented the findings of the studies during the consultation.

According to the information communicated by municipal representatives during the meeting, demolition and relocation/reconstruction were considered the only viable solution given the condition of the foundation and soil.

The article also confirms that the project had originally been presented as a renovation, estimated at approximately $1.6 million, including stabilization of the foundations.

It states that the Demolition Committee assessed the project according to 11 criteria, including structural integrity, historical significance and community impacts, before voting unanimously in favour of demolition.

Reference: William Crooks, The Record / Local Journalism Initiative, September 4, 2024

Read “North Hatley’s Pleasant View Beach House set to be replaced after unanimous demolition vote”


October 7, 2024: Council Upholds the Demolition Decision

On October 7, 2024, the matter returned to Municipal Council.

Resolution 2024-10-07.17 is probably the most important publicly available municipal document in the file.

It establishes, among other things, that:

  • the PRACIM project initially involved renovation;
  • the renovation was estimated at approximately $1,596,000;
  • a geotechnical study was requested;
  • the land survey confirmed that the building was located within constraint zones;
  • the geotechnical study and a structural analysis were received;
  • the structural analysis confirmed the fragility of the building;
  • according to that analysis, the building could not withstand being moved;
  • the Demolition Committee ruled in favour of demolition “in light of the studies and expert reports.”

Council then decided:

to uphold the decision of the Demolition Committee and continue the process associated with the demolition of the building for reconstruction.

This wording is particularly important because the Municipality explicitly acknowledges the existence of studies and expert reports that were used by the committee in reaching its decision.

Reference: Minutes of October 7, 2024 — Resolution 2024-10-07.17

View the October 7, 2024 municipal minutes


That Same Evening: Nearly $220,000 in Professional Mandates

During the same October 7, 2024 meeting, several professional contracts were awarded to move the reconstruction project forward:

ResolutionProfessionalMandateAmount
2024-10-07.18David Leslie ArchitectureArchitecture$109,500
2024-10-07.19Côté JeanCivil engineering$25,000
2024-10-07.20EXPMechanical and electrical engineering$45,000
2024-10-07.21Côté JeanStructural engineering$40,000
TOTAL$219,500

These contracts were in addition to the $12,350 geotechnical study and the $8,500 preliminary architectural mandate.

Reference: Minutes of October 7, 2024 — Resolutions 2024-10-07.18 to 2024-10-07.21

…

Comments (0)

No comments yet. Be the first to react.

Contribute to this article

Do you have useful information?

A cost, a document, a photo or a correction. Every piece of information is verified before being added to the article or to an issue.

Read also