Pleasant View: What do the studies reveal and on what technical findings did the demolition committee base its judgment that demolition is necessary?
Cover photo credit: Photo by William Crooks. Reference: https://qcna.qc.ca/north-hatleys-pleasant-view-beach-house-set-to-be-replaced-after-unanimous-demolition-vote/ It has now been over 30 days since the co
North Hatley Info
August 23, 2026 · 9 min read

Featured photo credit: Photo by William Crooks
Reference: https://qcna.qc.ca/north-hatleys-pleasant-view-beach-house-set-to-be-replaced-after-unanimous-demolition-vote/
It has now been more than 30 days since the construction contract for the new Pleasant View Community Centre was awarded, for a total of $4,078,000. View the contract on SEAO.
This contract marks the culmination of a long process that led the Municipality of North Hatley to pivot from an initial project to renovate the historic Pleasant View building, valued at approximately $1.596 M, to its demolition and the construction of a new building at a cost of $4.078 M in the coming weeks.
This evolution of the project was based on several professional studies, analyses, and reports. Some of these documents played a decisive role in the decision to demolish the building.
However, these documents, which are essential to understanding the decision, do not appear to be publicly accessible.
Expert studies and reports at the heart of the decision to authorize demolition
It is worth recalling that the geotechnical study, costing $12,350, as well as the structural analysis of the building, allowed the demolition committee, composed of elected officials Andrew J. Pelletier, Caroll Haller, and Danielle Dupré, to confirm the fragility of the structure, which prevented it from being moved and forced its demolition.
The resolution of October 7, 2024, states that the committee reached its decision "in light of the expert studies and reports."
It indicates:
June 2024:
- reception of the geotechnical study;
- structural analysis of the existing building.
Then, in:
August 2024:
- reception of the structural analysis;
- confirmation of the fragility of the structure.
The resolution further explains that the building is located in restricted zones and that the project is not eligible under the applicable regulatory framework in its current position, as it would be possible to move the building outside of these zones.
However, it adds a decisive element:
the structural study of the building demonstrates that its structure would not be able to withstand being moved, and that it would therefore be necessary to proceed with demolition for reconstruction.
It is therefore likely that between the return of the technical analyses in June and August 2024, the renovation project definitively shifted toward demolition followed by reconstruction.
Reference: Minutes of October 7, 2024 — resolution 2024-10-07.17
View the municipal minutes of October 7, 2024
Questions that remain
After more than two years of procedures and now that a $4.078 M contract has been awarded, several questions deserve documented answers:
What exactly did the Granulab geotechnical study conclude, and where can the report of this study be consulted?
What exactly did the structural analysis received in 2024 conclude, and where can the study report be consulted?
Which report determined that the building could not be moved, and where can this report be consulted?
What solutions for preserving the building were studied, and where can these solutions be consulted?
Was the reconstruction of the foundations, which was still part of the project in January 2024, subject to a comparative analysis, and where can this comparative analysis be consulted?
What were the estimated costs of the various solutions?
Which reports and expert opinions were presented to the three elected officials on the demolition committee before their vote?
The resolution of October 7, 2024, itself states that the committee reached its decision "in light of the expert studies and reports."
Making these documents accessible would simply allow citizens to review the same technical information that was used to reach the decision.
In a public project of this magnitude, this would make it clear what was studied, what was ruled out, and why.
From a renovation project to complete demolition
An important element of the file is sometimes forgotten: the project did not begin as a demolition project.
Resolution 2024-10-07.17 of the municipal council indicates that in May 2023, the Municipality had submitted an application for financial assistance to the PRACIM program specifically aimed at the renovation of the Pleasant View building.
The project was pre-selected at the time, and the estimated cost for the renovation and bringing the building up to code was approximately:
$1,596,000
Reference: Minutes of October 7, 2024 — resolution 2024-10-07.17
View the municipal minutes of October 7, 2024
January 2024: still planning to preserve the building
On January 23, 2024, the Municipality authorized a geotechnical study.
Resolution 2024-01-23.04 is particularly interesting because it still describes the project as a reconstruction/renovation project for the Pleasant View building.
It also specifies that the project was to include the reconstruction of the foundations.
The geotechnical study was necessary to evaluate the load-bearing capacity of the soil and foundations in relation to the project.
At that time, therefore, the complete demolition of the building did not yet seem to be the chosen solution.
Reference: Minutes of January 23, 2024 — resolution 2024-01-23.04
View the municipal minutes of January 23, 2024
March 2024: a $12,350 geotechnical study
On March 4, 2024, the council revisited the project.
Resolution 2024-03-04.08 still explicitly speaks of the:
“Pleasant View building renovation project”
It specifies that the geotechnical study is necessary to determine the exact structural recommendations required for the project.
Three companies were invited to bid:
- Granulab: $12,350
- FNX Innov: no bid
- NCL Envirotek: no bid
The contract was therefore awarded to Granulab for $12,350.
Reference: Minutes of March 4, 2024 — resolution 2024-03-04.08
View the municipal minutes of March 4, 2024
Demolition committee appointed in March 2024
During that same session on March 4, 2024, the council appointed the demolition committee.
According to resolution 2024-03-04.10, the municipal by-law requires the committee to be composed of three members of the municipal council.
The appointed members are:
- Andrew J. Pelletier — chair
- Caroll Haller — member
- Danielle Dupré — member
The same resolution appoints as alternates:
- Elizabeth Fee
- David Wilson
This composition is particularly relevant to the Pleasant View file, as this committee would be called upon a few months later to rule on the demolition of the building.
It is important to specify that this is therefore not an independent committee made up of experts in architecture, heritage, structural engineering, or geotechnical engineering: the three committee members are municipal elected officials.
Their decision was therefore to be based, in part, on the studies, analyses, and expert reports presented to them.
Reference: Minutes of March 4, 2024 — resolution 2024-03-04.10
View the municipal minutes of March 4, 2024
May and July 2024: preliminary plans
In May 2024, the council authorized a call for tenders for the creation of preliminary plans and specifications for the project.
The corresponding resolution is 2024-05-06.23.
Then, on July 8, 2024, the council awarded David Leslie Architecte a mandate of $8,500 plus taxes for preliminary architectural planning.
Interestingly, the July 8 resolution still describes the file as a:
Pleasant View building renovation project submitted to PRACIM.
Two offers had been received:
- Firme 1628 Inc.: $21,200
- David Leslie Architecte: $8,500
The contract was awarded to David Leslie.
References:
Minutes of May 6, 2024 — resolution 2024-05-06.23
View the municipal minutes of May 6, 2024
Minutes of July 8, 2024 — resolution 2024-07-08.13
View the municipal minutes of July 8, 2024
June and August 2024: the turning point
This is where the chronology becomes particularly interesting.
In its resolution of October 7, 2024, the Municipality reconstructs the steps that led to the demolition itself.
It indicates:
June 2024:
- return of the geotechnical study;
- structural analysis of the existing building.
Then:
August 2024:
- return of the structural analysis;
- confirmation of the fragility of the structure.
The resolution then explains that the building is located in restricted zones and that the project is not eligible under the applicable regulatory framework in its current position, since it would be possible to move the building out of these zones.
But it adds a decisive element:
the structural study on the building shows that its structure will not be able to withstand being moved, and therefore, it will be necessary to proceed with demolition for reconstruction.
It is therefore highly likely that between the return of the technical analyses in June and August 2024, the renovation project definitively shifted toward demolition followed by reconstruction.
Reference: Minutes of October 7, 2024 — resolution 2024-10-07.17
Consult the municipal minutes of October 7, 2024
September 3, 2024: public consultation on the demolition
A public consultation by the demolition committee was held on September 3, 2024.
An article from The Record, published the following day by QCNA and signed by William Crooks, offers a particularly interesting account of this meeting.
According to the article, the information presented during the consultation noted, among other things:
- a heavily deteriorated foundation;
- significant cracks;
- continuous movement of the building;
- unstable soil conditions;
- instability compared to "quicksand";
- stabilization that would have been costly and potentially temporary;
- the lack of a guarantee that stabilization would prevent further damage;
- the building's location in a flood zone and a riparian buffer strip.
The article also reports that the project manager presented the study findings during the consultation.
According to information provided by municipal representatives during this meeting, demolition and relocation/reconstruction were considered the only viable solution given the state of the foundation and the soil.
The article also confirms that the project had initially been presented as a renovation, estimated at approximately $1.6 M, which included the stabilization of the foundations.
It indicates that the demolition committee reviewed the project based on 11 criteria, including structural integrity, historical significance, and community impacts, before voting unanimously in favor of the demolition.
Reference: William Crooks, The Record / Local Journalism Initiative, September 4, 2024
Read the article “North Hatley’s Pleasant View Beach House set to be replaced after unanimous demolition vote”
October 7, 2024: the council ratifies the demolition
On October 7, 2024, the file returned before the municipal council.
Resolution 2024-10-07.17 is likely the most important public municipal document in the file.
It establishes, in particular, that:
- the PRACIM project initially aimed for renovation;
- this renovation was estimated at approximately $1,596,000;
- a geotechnical study was requested;
- the land survey confirmed the building's presence in restricted zones;
- the geotechnical study and a structural analysis were received;
- the structural analysis confirmed the fragility of the building;
- according to this analysis, the building could not withstand being moved;
- the demolition committee ruled in favor of demolition "in light of the studies and expert reports."
The council then decided:
to ratify the decision of the Demolition Committee and to continue the process associated with the demolition of the building for reconstruction.
This sentence is particularly important since the Municipality explicitly acknowledges the existence of studies and expert reports that served as the basis for the committee's decision.
Reference: Minutes of October 7, 2024 — resolution 2024-10-07.17
Consult the municipal minutes of October 7, 2024
The same evening: nearly $220,000 in professional mandates
During this same meeting on October 7, 2024, several professional contracts were awarded to pursue the reconstruction project:
| Resolution | Professional | Mandate | Amount |
|---|---|---|---|
| 2024-10-07.18 | David Leslie Architecture | Architecture | $109,500 |
| 2024-10-07.19 | Côté Jean | Civil Engineering | $25,000 |
| 2024-10-07.20 | EXP | Mechanical and Electrical | $45,000 |
| 2024-10-07.21 | Côté Jean | Structure | $40,000 |
| TOTAL | $219,500 |
These contracts are in addition to the $12,350 for the geotechnical study and the $8,500 for the preliminary architectural mandate.
…
Comments (0)
No comments yet. Be the first to react.
Contribute to this article
Do you have useful information?
A cost, a document, a photo or a correction. Every piece of information is verified before being added to the article or to an issue.